Earned Value Management (EVM)EVM Basics

The 4 Foundational EVM Values (PV, EV, AC, BAC)

Translating scope completion and spending into a common dollar baseline

Performance MeasurementHigh-Yield Exam Topic

Earned Value Management (EVM)

EVM combines scope, schedule, and cost baselines into objective dollar metrics so you know not just how much money was spent, but how much authorized value was actually delivered.

  • PV · EV · AC · BAC
  • CV · SV · CPI · SPI
  • EAC · ETC · VAC · TCPI
PV

Planned Value (BCWS)

How much work SHOULD be done by now

The authorized baseline budget assigned to the scheduled work up to the status date.

EV

Earned Value (BCWP) ★

How much authorized work IS actually done

The budgeted value of the work actually completed so far (EV = % Complete × BAC).

AC

Actual Cost (ACWP)

How much money WAS actually spent

The total realized cost incurred in accomplishing the work performed up to the status date.

BAC

Budget at Completion

Total authorized project budget

The sum of all budgets established for the entire project (equals the Cost Baseline).

Golden Rule of EVM Formulas
EV ALWAYS comes first! Whether calculating Cost or Schedule, Variances subtract from EV (EV − ...) and Indices divide EV by AC or PV (EV / ...).