PV
Planned Value (BCWS)
How much work SHOULD be done by now
The authorized baseline budget assigned to the scheduled work up to the status date.

Translating scope completion and spending into a common dollar baseline
EVM combines scope, schedule, and cost baselines into objective dollar metrics so you know not just how much money was spent, but how much authorized value was actually delivered.
How much work SHOULD be done by now
The authorized baseline budget assigned to the scheduled work up to the status date.
How much authorized work IS actually done
The budgeted value of the work actually completed so far (EV = % Complete × BAC).
How much money WAS actually spent
The total realized cost incurred in accomplishing the work performed up to the status date.
Total authorized project budget
The sum of all budgets established for the entire project (equals the Cost Baseline).
EV − ...) and Indices divide EV by AC or PV (EV / ...).