Mandatory
Hard Logic
Legally, contractually, or physically required (e.g., foundation before roof).

Locking the performance baseline and sequencing activities with logical relationships
Reliable schedules combine realistic duration estimates, clear logical dependencies, and disciplined trade-offs whenever deadlines tighten or resources peak.
| Logical Relationship | Meaning | Common Example |
|---|---|---|
| Finish-to-Start (FS) ★ | Successor cannot start until predecessor finishes | Write code → Deploy to test server (most common) |
| Start-to-Start (SS) | Successor cannot start until predecessor starts | Pour foundation → Start curing inspection checklist |
| Finish-to-Finish (FF) | Successor cannot finish until predecessor finishes | Write chapters → Complete final proofreading |
| Start-to-Finish (SF) | Successor cannot finish until predecessor starts (rare) | Old security shift ends when new shift clocks in |
Hard Logic
Legally, contractually, or physically required (e.g., foundation before roof).
Soft / Preferred
Best-practice sequence chosen by team; first candidate for Fast Tracking.
Outside Control
Depends on non-project party (vendor delivery, municipal permit).
Inside Control
Link between two project activities controlled by the team.