Total Float vs. Free Float
Two flavors of scheduling flexibility on non-critical activities:
- Total Float: Delay possible without delaying the PROJECT end date (LF − EF or LS − ES)
- Free Float: Delay possible without delaying any immediate SUCCESSOR’s Early Start