Critical Path Method (CPM)CPM Logic

CPM Core Concepts: Longest Path & Float

Why the longest network path defines the shortest possible project duration

Schedule Network AnalysisZero Float Path

Critical Path Method (CPM)

The Critical Path is the longest sequential path through the project network—representing the shortest possible time to finish the project with zero scheduling flexibility.

  • Longest Path = Shortest Duration
  • Total Float = 0 on Critical Path
  • Watch Near-Critical Paths
Critical Path Float
0 Days
Any delay shifts end date 1:1
Project Duration
Longest Path
Minimum feasible completion time
Multiple Critical Paths
Possible!
Tied longest paths double risk

Total Float vs. Free Float

Two flavors of scheduling flexibility on non-critical activities:

  • Total Float: Delay possible without delaying the PROJECT end date (LF − EF or LS − ES)
  • Free Float: Delay possible without delaying any immediate SUCCESSOR’s Early Start

Multiple & Near-Critical Paths

Never monitor only one path if rival paths are close behind:

  • Example: Path A = 12d, Path B = 8d, Path C = 12d → Duration = 12d with TWO critical paths (A & C)
  • Near-critical path: Small positive float (e.g., 1–2 days); minor delays wipe out float and create a new critical path