Cost ManagementEstimating

Cost Estimating Techniques & Accuracy Ranges

Selecting the right estimation method as scope clarity matures from Initiation to Planning

Budgeting & ReservesCost Baseline

Cost Management & Reserve Architecture

Accurate cost control starts with matching estimate precision to available WBS detail, protecting baselines with properly governed reserves, and ignoring sunk costs.

  • ROM · Budget · Definitive
  • Contingency vs. Management Reserve
  • Sunk Cost Fallacy
Four Cost Estimating Methods
MethodMechanismWhen to UseAccuracy & Cost
AnalogousScales historical actuals from similar past projectsEarly initiation when detail is scarce and speed mattersLowest accuracy · Fastest & cheapest
ParametricMultiplies statistical unit cost × quantity (e.g., $/sq ft)Reliable historical database & scalable deliverables existModerate–High · Fast when calibrated
Three-Point (PERT)Uses (O + 4M + P) / 6 to capture cost uncertaintyActivities carry significant price or vendor uncertaintyCaptures risk spread cleanly
Bottom-UpEstimates at Work Package level and rolls up totalsDetailed WBS exists and high precision is requiredHighest accuracy · Most time & effort

Estimate Accuracy Narrows Across the Project Lifecycle

Expect wide uncertainty ranges during Initiation and tight bounds once WBS Work Packages are priced.

Initiation (Low Detail)Detailed Planning (WBS Ready)

ROM Estimate

−25% to +75%

Rough Order of Magnitude

  • • Used in Initiating / Business Case
  • • Driven by Analogous estimating

Budget Estimate

−10% to +25%

Preliminary Funding

  • • Early-to-mid Planning
  • • Drives capital allocation approvals

Definitive Estimate

−5% to +10%

Cost Baseline Ready

  • • Late Planning with full WBS
  • • Driven by Bottom-Up estimating