Cost ManagementEstimating
Cost Estimating Techniques & Accuracy Ranges
Selecting the right estimation method as scope clarity matures from Initiation to Planning
Budgeting & ReservesCost Baseline
Cost Management & Reserve Architecture
Accurate cost control starts with matching estimate precision to available WBS detail, protecting baselines with properly governed reserves, and ignoring sunk costs.
- ROM · Budget · Definitive
- Contingency vs. Management Reserve
- Sunk Cost Fallacy
| Method | Mechanism | When to Use | Accuracy & Cost |
|---|---|---|---|
| Analogous | Scales historical actuals from similar past projects | Early initiation when detail is scarce and speed matters | Lowest accuracy · Fastest & cheapest |
| Parametric | Multiplies statistical unit cost × quantity (e.g., $/sq ft) | Reliable historical database & scalable deliverables exist | Moderate–High · Fast when calibrated |
| Three-Point (PERT) | Uses (O + 4M + P) / 6 to capture cost uncertainty | Activities carry significant price or vendor uncertainty | Captures risk spread cleanly |
| Bottom-Up | Estimates at Work Package level and rolls up totals | Detailed WBS exists and high precision is required | Highest accuracy · Most time & effort |
Estimate Accuracy Narrows Across the Project Lifecycle
Expect wide uncertainty ranges during Initiation and tight bounds once WBS Work Packages are priced.
Initiation (Low Detail)Detailed Planning (WBS Ready)
ROM Estimate
−25% to +75%Rough Order of Magnitude
- • Used in Initiating / Business Case
- • Driven by Analogous estimating
Budget Estimate
−10% to +25%Preliminary Funding
- • Early-to-mid Planning
- • Drives capital allocation approvals
Definitive Estimate
−5% to +10%Cost Baseline Ready
- • Late Planning with full WBS
- • Driven by Bottom-Up estimating