Scope BaselineScope Baseline
The Scope Baseline Triad & Integrated Updates
Three approved documents forming the baseline against which all scope performance is measured
Baseline GovernanceBaseline Triad
The Scope Baseline & Scope Control
Once approved, the Scope Baseline locks down project boundaries. Any deviation demands variance analysis and formal Integrated Change Control.
- Scope Statement + WBS + WBS Dictionary
- Scope Creep vs. Gold Plating
- Validate Scope vs. Control Scope
The 3 Components of the Scope Baseline
All three documents are approved together and can only be modified via formal Change Control.
1. Project Scope Statement
Boundaries- Deliverables & product description
- Acceptance criteria
- Explicit project exclusions
- Assumptions & constraints
2. Work Breakdown Structure
Hierarchy- 100% hierarchical decomposition
- Control Accounts & Planning Packages
- Work Packages at lowest level
3. WBS Dictionary
Details- ID codes & scope narrative
- Responsible owners
- Quality & acceptance specs
- Cost & milestone references
Integrated Baseline Ripple Effect
Baselines do not live in isolation. When an approved change alters the Scope Baseline, the PM MUST also review and update the Schedule Baseline and Cost Baseline as needed.
Scope Variance Analysis
Variance analysis in scope management compares the approved Scope Baseline against actual scope delivered to detect gaps and trigger corrective action.