WBS DecompositionWBS Architecture
Visual WBS Hierarchy & The 100% Rule
Deliverable-oriented decomposition capturing 100% of project scope—no more, no less
Create WBSDeliverable-Oriented
WBS Decomposition & The 100% Rule
The Work Breakdown Structure breaks down 100% of project deliverables into manageable Work Packages that can be reliably estimated, scheduled, and controlled.
- 100% Rule
- Work Packages = Lowest Level
- WBS Templates Save Time
Deliverable-Oriented WBS Hierarchy Example
Every branch sums up to 100% of its parent element; Level 4 represents assignable Work Packages.
Level 1 · Project (1.0)
Customer Portal Release
1.1 Control Account
Project Management
1.1.1 Initiation & Charter
1.1.2 Governance & Closure
1.2 Control Account
Core Web Application
1.2.1 Auth Module (Work Pkg)
1.2.2 Billing Engine (Work Pkg)
1.2.3 Reporting UI (Work Pkg)
1.3 Control Account
Verification & Rollout
1.3.1 Security Audit (Work Pkg)
1.3.2 User Training (Work Pkg)
The 100% Rule
The WBS must capture 100% of project and product scope—including project management and compliance deliverables—no more, no less. Missing scope causes rework; extra scope equals gold plating.
Reusing WBS Templates
Reusing a past similar project’s WBS as a starting baseline is called using a WBS Template (an OPA best practice that accelerates planning and prevents omissions).