A project has EV = $50K, AC = $60K, PV = $55K. What are the CPI and SPI?
CPI = 0.83 (over budget), SPI = 1.1 (ahead)
CPI = 0.83 (over budget), SPI = 0.91 (behind schedule)
CPI = 1.2 (under budget), SPI = 0.91 (behind)
CPI = 1.2 (under budget), SPI = 1.1 (ahead)