Slide View20 min
EVM Formula DrillsS-Curve Visual

Visual S-Curve Guide: Reading PV, EV & AC Together

Spotting schedule delays, cost overruns, and forecast gaps instantly from cumulative curves

Applied EVM PracticeInteractive Practice

S-Curves & Worked EVM Drills

Translate raw EVM numbers into visual S-Curves and build rapid calculation fluency so multi-step forecasting questions become guaranteed points on exam day.

  • Visual S-Curve Diagnostics
  • 3 Complete Worked Drills
  • TCPI Realism Checks

EVM S-Curve Diagnostic Chart (Over Budget & Behind Schedule Scenario)

At the Status Date (Time Now), AC > PV > EV: spending exceeds plan while delivered value trails both plan and actual cost.

BAC (Authorized Budget)EAC (Forecast)Status Date (Time Now)AC (Actual Cost)PV (Planned Value)EV (Earned Value)CV = EV − AC (−)SV = EV − PV (−)Cumulative Cost ($)Time →
Reading Schedule on the S-Curve
Compare EV vs. PV: if the EV curve sits below PV, you are behind schedule (negative SV). If EV sits above PV, you are ahead of schedule.
Reading Cost on the S-Curve
Compare EV vs. AC: if the EV curve sits below AC, you are over budget (negative CV)—you paid more than the value earned.
1 / 4