Schedule ManagementSequencing

Schedule Baseline & PDM Dependencies

Locking the performance baseline and sequencing activities with logical relationships

Chapter 5 · Process DomainSchedule Baseline

Schedule Planning, Dependencies & Compression

Reliable schedules combine realistic duration estimates, clear logical dependencies, and disciplined trade-offs whenever deadlines tighten or resources peak.

  • PDM Relationships (FS/SS/FF/SF)
  • Leads & Lags
  • PERT 3-Point Estimating
  • Crashing vs. Fast Tracking
What Is the Schedule Baseline?
The Schedule Baseline is the approved version of the schedule model used to measure and track actual progress. It can only be modified through formal Change Control—never confuse it with the latest working update.
Precedence Diagram Method (PDM) — 4 Logical Relationships & 4 Dependency Types
Logical RelationshipMeaningCommon Example
Finish-to-Start (FS) ★Successor cannot start until predecessor finishesWrite code → Deploy to test server (most common)
Start-to-Start (SS)Successor cannot start until predecessor startsPour foundation → Start curing inspection checklist
Finish-to-Finish (FF)Successor cannot finish until predecessor finishesWrite chapters → Complete final proofreading
Start-to-Finish (SF)Successor cannot finish until predecessor starts (rare)Old security shift ends when new shift clocks in

Mandatory

Hard Logic

Legally, contractually, or physically required (e.g., foundation before roof).

Discretionary

Soft / Preferred

Best-practice sequence chosen by team; first candidate for Fast Tracking.

External

Outside Control

Depends on non-project party (vendor delivery, municipal permit).

Internal

Inside Control

Link between two project activities controlled by the team.

1 / 4