Question 1/15
Single Answer
Analyze
A project is 40% complete. The planned value (PV) is $200,000, the actual cost (AC) is $220,000, and the earned value (EV) is $180,000. How is the project performing?
Behind schedule and under budget.
Behind schedule and over budget.
Ahead of schedule and under budget.
Ahead of schedule and over budget.
Submit Answer