Mock Exam 3 - Scenario Question 1: A project is in execution when a new regulatory standard is published. Non-compliance could result in massive fines. What should the PM do first?
Submit a change request to modify the project deliverables.
Halt all project work immediately.
Request additional compliance budget from the sponsor.
Acknowledge the change and initiate an impact analysis on the project scope, schedule, and cost with the team.